Manufacturing · 2023 · Ogun State, Nigeria
Industrial Fabrication Plant
A 14,000 m² long-span steel manufacturing facility with integrated crane gantries, mezzanine offices and heavy machine foundations.
Engineering Challenges
- C145-metre clear spans with 20-tonne travelling crane loads
- C2Vibration-sensitive machine bases adjacent to press lines
- C3Live commissioning of phase one during phase two erection
Solutions
- S1Tapered welded plate-girder portals fabricated in-house
- S2Isolated mass-concrete foundations with elastomeric bearings
- S3Hard-segregated erection zones with independent access routes
Gallery
On site.
Results
Measured outcomes.
14,000 m²
Covered production area
2,100 t
Structural steel erected
11 months
Concept to commissioning